Advertisement

April 20, 2014

Sixth Circuit Court of Appeals Rules that U.S. Environmental Protection Agency (USEPA) May Proceed with an Enforcement Action against DTE Energy

On March 28, 2013, the Sixth Circuit Court of Appeals ruled that the U.S. Environmental Protection Agency (USEPA) did not need to wait until post-construction emissions data became available to challenge DTE Energy Corp.’s projection that a construction project was not a “major modification,” and, thus, did not require a New Source Review (NSR) construction permit under USEPA’s Clean Air Act regulations.  (United States v. DTE Energy Co., 6th Cir., No. 11-2328).  In so ruling, the Sixth Circuit reversed a district court order that provided a safe harbor for owners and operators of sources that complied with pre-project recordkeeping and reporting requirements from USEPA enforcement until and unless post-project emissions data demonstrated that the projection was incorrect.

In 2010, DTE undertook construction on a project at its Monroe Power Plant in Monroe, Michigan.  Prior to initiating construction, DTE performed the required pre-project emission projections and determined that the project would not increase emissions sufficient to require a permit under the NSR regulations.  In accordance with state and federal regulations, DTE submitted its projections to the state permitting agency and began construction.  A few months later, USEPA challenged DTE’s pre-project projection in federal court, alleging that the project resulted in a “significant net emissions increase” and required a NSR construction permit.

On appeal, the Sixth Circuit confirmed that the NSR regulations cannot be read to provide USEPA with the authority to “second-guess” a source’s pre-project projections.  Such an interpretation would effectively transform a “project-and-report scheme … into a [required] prior approval scheme,” which the court noted was inconsistent with the plain language of the regulations.  Nonetheless, the Sixth Circuit found that contrary to the district court’s ruling, nothing under the regulations precluded USEPA from bringing an enforcement action at any time to “ensure that the [pre-]project projection [was] made pursuant to the requirements of the regulations.”  In other words, USEPA does not need to wait until post-construction emissions data becomes available to challenge a source’s pre-project emission projections.  It is worth noting, however, that the dissent called the majority opinion “logically flawed and … legally incorrect” on grounds that the court’s opinion was inherently contradictory.  As the dissent explained, the NSR regulations do not require pre-construction approval from USEPA, but “if the USEPA can challenge the operator’s scientific preconstruction emission projections in court … that is the exact same thing as requiring prior approval.

Notably, the Sixth Circuit did not side with USEPA carte blanche.  The court was quick to point out that its reversal did “not constitute endorsement of USEPA’s suggestion[]” that DTE’s pre-project projection should have demonstrated that the project constituted a major modification and required an NSR permit.  And the court challenged USEPA’s suggestion that a source could not intentionally limit generation to limit its post-project emissions that otherwise could retroactively require a NSR permit.

The Sixth Circuit remanded the case to the district court for further proceedings on whether the DTE project did or did not constitute a major modification and require a NSR construction permit.

© 2014 Schiff Hardin LLP

About the Author

David M. Loring, Associate, Schiff Hardin Law Firm
Associate

David M. Loring is a senior associate concentrating his practice in all areas of environmental law. Mr. Loring has counseled and represented electric generating and large industrial clients on a variety of federal, state and administrative litigation and regulatory matters, including:

  • Negotiation of a multi-facility Clean Air Act New Source Review (NSR) settlement agreement between an electric generating utility and the United States
  • Defense of an NSR enforcement action brought by the United States against an electric generating utility
  • ...
312-258-5603

Boost: AJAX core statistics

Legal Disclaimer

You are responsible for reading, understanding and agreeing to the National Law Review's (NLR’s) and the National Law Forum LLC's  Terms of Use and Privacy Policy before using the National Law Review website. The National Law Review is a free to use, no-log in database of legal and business articles. The content and links on www.NatLawReview.com are intended for general information purposes only. Any legal analysis, legislative updates or other content and links should not be construed as legal or professional advice or a substitute for such advice. No attorney-client or confidential relationship is formed by the transmission of information between you and the National Law Review website or any of the law firms, attorneys or other professionals or organizations who include content on the National Law Review website. If you require legal or professional advice, kindly contact an attorney or other suitable professional advisor.  

Some states have laws and ethical rules regarding solicitation and advertisement practices by attorneys and/or other professionals. The National Law Review is not a law firm nor is