FERC Will Require All New Nonsynchronous Generators to Provide Frequency Response

In response to concerns that the ability of the electric system to provide frequency response following a system disturbance is falling across the United States, the Federal Energy Regulatory Commission (FERC) changed its generation interconnection requirements on February 15. Frequency response is, generally speaking, the ability of the system to quickly return to 60 Hz frequency following a system event such as the sudden loss of a generator. If frequency is not immediately corrected, over- or under-frequency events can occur, which would lead to more and more facilities tripping out of service. The ability of the bulk electric system to provide frequency response is therefore critical in order to avoid cascading outages.

Under the revisions to the pro forma Large Generator Interconnection Agreement (LGIA) and the Small Generator Interconnection Agreement (SGIA), nonsynchronous generators (typically renewable generation) will for the first time be required to have equipment that enables the generator to provide frequency response. Previously, only synchronous generators were required to have that capability because of concerns that nonsynchronous generators were not technically capable of providing that service. FERC found that with recent technological developments there is no longer a reason to treat synchronous and nonsynchronous generation differently on this issue.

The new requirements will apply only to new interconnection agreements, including those driven by changes at an existing generator that necessitate a new interconnection agreement.

Copyright © 2019 by Morgan, Lewis & Bockius LLP. All Rights Reserved.

TRENDING LEGAL ANALYSIS


About this Author

J. Daniel Skees, Energy attorney, Morgan Lewis
Partner

J. Daniel Skees represents electric utilities before the Federal Energy Regulatory Commission (FERC) and other agencies on rate, regulatory, and transaction matters. He handles rate and tariff proceedings, electric utility and holding company transactions, reliability standards development and compliance, and FERC rulemaking proceedings. The mandatory electric reliability standards under Section 215 of the Federal Power Act are a major focus of Dan’s practice. He advises clients regarding compliance with reliability standards, and helps them participate in the...

202-739-5834