New Ratemaking Order Revamps Conventional Cost-of-Service Ratemaking for New York Utilities

The State is Seeking to Align Utility Business Models With REV Policy

Objectives

Summary:  On May 19, 2016, the New York Public Service Commission adopted an order setting forth a new model framework for ratemaking and utility revenue (Ratemaking Order) within the Reforming the Energy Vision program.  The Ratemaking Order provides nine measures that the Commission expects will help utilities and other stakeholders transition to the new framework.  This alert highlights two of the nine measures and provides key upcoming deadlines established by the Ratemaking Order.

On May 19, 2016, the New York Public Service Commission (the Commission) adopted an order setting forth a new model framework for ratemaking and utility revenue (Ratemaking Order) within the Reforming the Energy Vision (REV) program.  The order builds on the 2015 Framework Order, which adopted a regulatory policy framework for REV, and, as articulated in the agency’s 2016 Order Authorizing the Clean Energy Fund Framework,  advances one of REV’s four major pillars by moving away from the current conventional approach to ratemaking.  The Commission drew on three principles articulated in the Framework Order:

First, the unidirectional grid must evolve into a more diversified and resilient distributed model engaging customers and third parties.  Second, ensuring universal, reliable, resilient, and secure delivery service at just and reasonable prices remains a function of regulated utilities. Third, and critically important to this order, the overall efficiency of the system and consumer value and choice must be improved by achieving a more productive mix of utility and third-party investment.

With these principles in mind, the Ratemaking Order delineates boundaries for a “modern regulatory model” that augments conventional cost-of-service ratemaking by adding outcome-based incentives. The new model aims for increased efficiency, transparency, and resiliency, as well as greater engagement with customers and third parties, while creating financial incentives to utilities that pursue REV activities such as Distributed Energy Resource (DER) integration and grid modernization.  Drawing on experience in other sectors, competitors may accomplish these goals through “coopetition” – or by undertaking joint efforts under a reconfigured service platform that facilitates shared earning opportunities.  Specifically, the Ratemaking Order provides nine measures1 that the Commission expects will help utilities and other stakeholders transition to the new framework, two of which are highlighted here.

First, the Ratemaking Order initiates two key forms of earning opportunities: platform service revenues and earning adjustment mechanisms.

  • Platform service revenues (PSRs) are “new forms of utility revenues associated with the operation and facilitation of distribution level markets.”  Utilities initially may generate revenues by replacing traditional infrastructure with “non-wires alternatives” (e.g., demand side management programs), and eventually adding new services that can be performed by third parties.  The Commission recognized that revenues from PSRs must be shared, and established as presumptively “reasonable” an allocation of 80% to ratepayers and 20% to the utility’s shareholders; this allocation is a starting point that may be revisited.  The Commission also streamlined the tariff review and approval process for PSRs.

  • Earning adjustment mechanisms (EAMs), which can be viewed as near-term measures to be undertaken to complement the development of PSRs, aim to increase energy and system efficiencies and further engage customers in efficiency efforts. EAMs will be framed around outcome-based incentives that encourage innovation.  The Commission identified specific EAM opportunity areas that utilities should pursue such as “ambitious” peak reduction and load factor improvement targets, and energy efficiency measures.

In another proceeding, the Commission is also considering a Clean Energy Standard (CES) under REV to achieve greenhouse gas reduction targets, and utilities should have future earning opportunities “tied to reducing the cost of achieving the CES goal.” 

Second, the Ratemaking Order explored rate design improvement opportunities.  For example, large commercial and industrial customers are already subject to demand-based rates for delivery, and hourly rates for commodity service.  The Commission has directed utilities to evaluate reforms that make these rates more peak-sensitive or by changing the determinants such as peak-to-off-peak ratios that influence customer decisions. 

The initiatives set forth in the Ratemaking Order are being tested by Con Edison, in partnership with SunPower Corp., with the unveiling of a “Virtual Power Plant.”  The Virtual Power Plant is an integrated solar and storage plan consisting of residential solar/battery installations, that offers an alternative tariff structure and has been offered to 300 homeowners in New York. Con Edison would be able to draw power from the Virtual Power Plant to supply power to the grid during periods of peak demand.  It is an experimental program that aligns the Ratemaking Order measures with the REV goal to achieve greater resiliency and renewable energy sources. 

The Ratemaking Order has established the following deadlines:

  • August 1, 2016

    • Utilities other than Con Edison to file revisions to for standby tariffs

    • Utilities other than Con Edison to file interconnection survey process and EAM

  • September 1, 2016 

    • Utilities other than Con Edison to file progress report on aggregated data reporting efforts

  • October 1, 2016

    • Clean Energy Advisory Council will propose metrics and targets 

    • Utilities other than Con Edison to file data privacy policy statement 

    • Utilities other than Con Edison to file review of standby rate allocation matrix with proposed revisions

  • December 1, 2016

    • Utilities are to file system efficiency proposal

  • February 1, 2017 

    • Utilities other than Con Edison to file one or more Smart Home Rate demonstration proposals 

  • June 1, 2017 

    • Utilities other than Con Edison to file revisions to voluntary time of use rates and promotion and education tools (by June 1, 2017 for utilities with rate plans that expire after January 1, 2018 or in next rate filing)

© 2020 Beveridge & Diamond PC National Law Review, Volume VI, Number 182

TRENDING LEGAL ANALYSIS


About this Author

Michael G. Murphy Energy & Land Use Attorney Beveridge & Diamond New York, NY
Principal

Michael provides concrete, pragmatic advice that helps clients solve problems and achieve their goals in matters involving energy, land use, permitting, compliance, contracts, and litigation.

He worked for several years in construction before earning his undergraduate degree in Environmental Science and making a decision to enter the practice of environmental law. Today, he follows a similar non-traditional path in advising his clients—eschewing cookie-cutter approaches. He dives into the factual and legal issues, learning what is unique about his client, and tailors his advice to...

212-702-5436
John H. Paul Environmental & Energy Attorney Beveridge & Diamond New York, NY
Principal

John's practice focuses on environmental and energy law, project development, and environmental quality review of project proposals.

He assists clients in permitting, regulatory compliance, and enforcement matters involving waste management and disposal, hazardous wastes, bulk storage, wastewater, and air emissions. He advises clients with regard to remediation of contaminated properties and brownfield development, particularly on properties involving multiple ownership interests and complicated histories. He also advises and represents property owners and developers with regard to laws governing the development and use of waterfront and wetland properties.

John works with project development teams in planning, permitting, contracting, and transactions in support of large-scale development. This work has included energy and transmission projects on brownfields and municipally-owned properties, as well as submarine and wetland installations. Environmental impact review is a fundamental part of this work, and John helps clients manage the process to streamline review in support of reliable and defensible agency approvals.

John’s litigation practice includes federal and state class action defense, cost recovery, enforcement defense, and defense of citizen suits on behalf of site owners and operators, municipalities, and past owners of contaminated properties.

While at Pace University School of Law, John was awarded the White Plains Bar Association's Environmental Law Scholar Award. He served as Managing Editor of the Pace Environmental Law Review for 2002-2003. Before entering law school, John served in the U.S. Peace Corps in the Republic of Moldova, where he was an Associate Professor of English at the Moldovan state university.

212-702-5456
Sarah A. Kettenmann Environmental Attorney Beveridge & Diamond New York, NY
Associate

Sarah uses her knowledge of environmental law and the physical sciences to help clients solve complex problems in a conservation-minded manner.

She maintains a diverse environmental practice, which includes litigation matters involving toxic torts and products liability and class action litigation concerning environmental and regulatory claims. Her regulatory practice includes advising clients on compliance with, and enforcement of, land use restrictions and remediation, and due diligence for waste facility permits under federal and state statutes. She also counsels clients on...

212-702-5425