HB Ad Slot
HB Mobile Ad Slot
Indiana Utility Regulatory Commission Provides More Guidance on Future Test Year
Thursday, February 1, 2018

On Jan. 24, the Indiana Utility Regulatory Commission issued its final order in Community Utilities of Indiana Inc. (CUII), Cause No. 44724. Since the Indiana General Assembly enacted IC 8-1-2-42.7 authorizing either the use of a future test year or a hybrid test period in rate cases, the commission has grappled with the interplay between Section 42.7’s requirement that rates be approved based upon projected data and the requirement of IC 8-1-2-6 that rate base include a plant that is actually in service.

CUII is the first non-settled future test year case, and the commission explained one method for how rates, over the course of the future test year, can reflect plant that is actually in service. Rates approved in the Order reflect projections of all components of rate base through the end of the future test year, and not just those particular major plant additions identified by the petitioner in evidence. In CUII’s case, its projected rate base serves as a cap. CUII is required to file an updated tariff, a certification as to the plant that has actually been placed in service, and detailed plant accounting information. Other parties are provided an opportunity to conduct discovery and request a hearing. This methodology is similar to one that had previously been approved as a part of a settled future test year rate case.

 

HB Ad Slot
HB Mobile Ad Slot
HB Ad Slot
HB Mobile Ad Slot
HB Ad Slot
HB Mobile Ad Slot
 

NLR Logo

We collaborate with the world's leading lawyers to deliver news tailored for you. Sign Up to receive our free e-Newsbulletins

 

Sign Up for e-NewsBulletins